For the week of June 1st, anticipated work from CTH Z to Ridgeway includes:
- Eastbound –
-
- Milling
- Asphalt paving of the passing lane
- Aggregate Shoulder
Westbound –
- * Aggregate shoulder
-
- Guard Rail installation
- Milling
- Asphalt paving of the passing lane
- Asphalt paving of median crossovers
- The median at CTH Y/YZ will be CLOSED to cross traffic and left turning traffic on Monday, Wednesday and Thursday to complete surface paving operations. Only Right Turns will be allowed in and out of CTH Y and CTH YZ
Work will resume from Ridgeway to East County Line mid-week, and single lane closures will occur. The contractors have items to finish at various locations throughout this 9 mile stretch.
Speed limit is reduced to 55mph throughout the work zone. Please slow down and drive with caution through all work zones!
For more information, please visit the project website: