The contractors are trying to get the remainder of the surface layer paved eastbound. The weather hasn’t been cooperating, as I am sure you all have witnessed the snow!
For the week of November 4th, anticipated work includes:
Work in the westbound lanes:
- Punch list items
Work in the eastbound lanes will shift daily for paving, typically working from the west towards the east:
- Right/driving lane anticipated to be closed Friday 11/1 and Saturday 11/2 to finish shoulder
- Left/passing lane anticipated to be closed starting Monday
- Guard rail and shoulder may begin
NOTE that disruption will occur at side roads and median crossovers/intersections during surface paving. Traffic looking to cross may be restricted for 10-15 minutes until the roller has passed.
The speed limit is reduced to 55mph throughout the work zone both eastbound and westbound
For more information, please visit the project website:
https://projects.511wi.gov/us18151/