Construction Updates

image002.jpg?id=16605&token=5c8068c85af20a0b32d033cc02e95711Asphalt paving is almost complete from Dodgeville to Ridgeway on USH 18.  Crews are placing the final lift of asphalt.  Work will continue over the next couple of weeks to finish shouldering, guard rail and pavement markings.

 

For the week of June 1st, anticipated work from CTH Z to Ridgeway includes:

  • Eastbound –
    • Milling
    • Asphalt paving of the passing lane
    • Aggregate Shoulder

Westbound –

  •         *  Aggregate shoulder
    • Guard Rail installation
    • Milling
    • Asphalt paving of the passing lane
    • Asphalt paving of median crossovers
    • The median at CTH Y/YZ will be CLOSED to cross traffic and left turning traffic on Monday, Wednesday and Thursday to complete surface paving operations.  Only Right Turns will be allowed in and out of CTH Y and CTH YZ 

Work will resume from Ridgeway to East County Line mid-week, and single lane closures will occur. The contractors have items to finish at various locations throughout this 9 mile stretch.

Speed limit is reduced to 55mph throughout the work zone. Please slow down and drive with caution through all work zones!

For more information, please visit the project website:

https://projects.511wi.gov/us18151/