image002.jpg?id=16929&token=3ba97b9de6b44a3d598098301910b054Despite the heat and storms that rolled through the area this week, a lot of work was accomplished! Asphalt paving finished yesterday.  Work will continue over the next couple of weeks to finish shouldering, guard rail, pavement markings, and miscellaneous items.

 

For the week of June 8th, anticipated work from CTH Z to Ridgeway includes:

  • Eastbound –
    • Aggregate Shoulder
    • Pavement Marking
    • Miscellaneous items

 

  • Westbound –
    • Aggregate shoulder
    • Pavement Marking
    • Miscellaneous Items

 

Anticipated work from Ridgeway to East County Line:

  • Single lane closures
  • Pavement Marking
  • Guard Rail work at E Brigham and W Brigham
  • Miscellaneous items

 

Speed limit is reduced to 55mph throughout the work zone. Please slow down and drive with caution through all work zones!

 

For more information, please visit the project website:

https://projects.511wi.gov/us18151/