USH 18/151 Iowa County – Weekly Construction Update for weeks of November 25th and December 2nd


Subject: 1204-05-72 USH 18/151 Iowa County – Weekly Construction Update for weeks of November 25th and December 2nd

A little warm up this past week allowed surface paving to finish Friday evening.  Aggregate shoulder, guard rail, pavement marking and rumble strips remain to be completed over the next few weeks.  Contractors are working today and tomorrow on a few items. 

 For the week of November 25th, anticipated work includes:

 Eastbound Right/driving lanewill close from Pikes Peak to CTH ID for aggregate shoulder and installation of guard rail

  • All traffic lanes will be opened by noon on Wednesday for the Thanksgiving Holiday

 For the week of December 2nd, anticipated work includes:

  • Eastbound Right/driving lane will close from Pikes Peak to CTH ID for aggregate shoulder and installation of guard rail
  • Rumble strips will be installed in the westbound and eastbound direction. This is a moving operation and will be followed by slow moving crash vehicle. 

The speed limit is reduced to 55mph throughout the work zone in the eastbound direction

 For more information, please visit the project website:
https://projects.511wi.gov/us18151/