1204-05-72 USH 18 Iowa County – Construction updates

The pavement rehabilitation project continues.  Work in 2020 will perform pavement rehabilitation on USH 18 from Dodgeville to Ridgeway.  Due to the unexpected cold weather last fall, there is some work to finish in the section from Ridgeway to Blue Mounds.

Lane closures on USH 18 are anticipated.  Please slow down and drive with caution through all work zones!

For the week of April 13th, anticipated work from CTH Z to Ridgeway includes:

  • Eastbound –
    • Sawing of concrete
    • Removal of concrete (work will begin at 5am)
    • Pouring of concrete base patching
    • Concrete curing
  • Westbound –
    • Sawing of concrete
    • Later in the week, removal of concrete (work will begin at 5am)
    • Pouring of concrete base patching
    • Concrete curing

Speed limit is reduced to 55mph throughout the work zone.

For more information, please visit the project website:

https://projects.511wi.gov/us18151/