Weekly Construction Update for week of November 4th


The contractors are trying to get the remainder of the surface layer paved eastbound.  The weather hasn’t been cooperating, as I am sure you all have witnessed the snow!   

For the week of November 4th, anticipated work includes:

Work in the westbound lanes:

  • Punch list items

Work in the eastbound lanes will shift daily for paving, typically working from the west towards the east:

  • Right/driving lane anticipated to be closed Friday 11/1 and Saturday 11/2 to finish shoulder
  • Left/passing lane anticipated to be closed starting Monday
  • Guard rail and shoulder may begin

NOTE that disruption will occur at side roads and median crossovers/intersections during surface paving.  Traffic looking to cross may be restricted for 10-15 minutes until the roller has passed.

The speed limit is reduced to 55mph throughout the work zone both eastbound and westbound

For more information, please visit the project website:
https://projects.511wi.gov/us18151/