USH 18/151 Iowa County – Weekly Construction Update for week of October 14th


Eastbound asphalt paving has begun!

For the week of October 14th, anticipated work includes:

Work in the westbound lanes:

  • Left/passing lane closed for
    • Adjustment of guard rail
    • shoulders
    • permanent pavement marking

Work in the eastbound lanes will shift daily for paving, typically working from the west towards the east:

  • Left/passing lane anticipated to be closed on Monday and Tuesday
  • Right/driving lane anticipated to be closed Wednesday thru Saturday
  • CTH ID ramps to be closed on Wednesday

 The speed limit is reduced to 55mph throughout the work zone both eastbound and westbound

For more information, please visit the project website:  https://projects.511wi.gov/us18151/