This week crews continued stage 3 of the project – base patching for the westbound driving lane. Next week work increases as contractors start on the eastbound lanes
For the week of August 19th, here is the anticipated work:
Support: Please remove the current Spotlight & post the following for this week. Thank you for your time. Nancy Parkos – Clerk
Work in the westbound lanes includes:
- Right/Driving lane closed from E County Line to CTH ID
- Work on the bridge over S. Jones Street
- Grading
- Cleanup
- Right/Driving Lane closed from Pikes Peak Road to the Ridgevue/CTH BB/CTH HHH Interchange in Ridgeway
- Base patching
- Cleanup
- Right/Driving lane closed from CTH K to Pikes Peak starting Wednesday
- Work on the bridge over S. Jones Street
- Sawing
- Base Patching
Work in the eastbound lanes:
- Right/Driving lane closed from Ridgevue/CTH BB/CTH HHH Interchange to Pikes Peak Monday and Tuesday
- Milling and paving asphalt shoulder
- Filling of concrete rumble strips
- Right/Driving lane closed from CTH ID to E County Line Monday and Tuesday
- Milling and paving asphalt shoulder
- Filling of concrete rumble strips
- Right/Driving lane closed from Pikes Peak to CTH ID on Wednesday
- Milling and paving asphalt shoulder
- Filling of concrete rumble strips
- Left/Passing lane closed starting Thursday from Ridgevue/CTH BB/CTH HHH Interchange to Pikes Peak and CTH ID to E County Line
- Sawing of centerline for future replacement
The speed limit is reduced to 55mph throughout the work zone.
For more information, please visit the project website:
https://projects.511wi.gov/us18151/